8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1 Assignment lecture #3 1. Construct an AON network based on the following: ACTIVITY IMMEDIATE

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1

Assignment lecture #3
1. Construct an AON network based on the following:

ACTIVITY IMMEDIATE PREDECESSOR(S)
A –
B –
C –
D A, B
E C

2. Insert a dummy activity and event to correct the following AOA network:

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 2

Assignment (cont’d)
3. The City Commission of Nashville has decided to build a botanical garden and picnic area in

the heart of the city for the recreation of its citizens. The precedence table for all the
activities required to construct this area successfully is given.

CODE ACTIVITY DESCRIPTION
TIME (IN
HOURS)

IMMEDIATE
PREDECESSOR(S)

A Planning Find location; determine resource requirements 20 None
B Purchasing Requisition of lumber and sand 60 Planning
C Excavation Dig and grade 100 Planning
D Sawing Saw lumber into appropriate sizes 30 Purchasing
E Placement Position lumber in correct locations 20 Sawing, excavation
F Assembly Nail lumber together 10 Placement
G Infill Put sand in and under the equipment 20 Assembly
H Out-fill Put dirt around the equipment 10 Assembly
I Decoration Put grass all over the garden, landscape, paint 30 Infill, out-fill

a) Draw the Gantt chart for the whole construction activity.
b) Draw the AON network for the construction activity.
c) Draw the AOA network for the construction activity.

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 3

Assignment (cont’d)
4. The planning department of an electronics firm has set up the activities for developing and production of a

new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a
five-day workweek and the project starts on January 4, 2020.

Activity ID Description Activity Predecessor Activity Time (weeks)

1 Staff None 2
2 Develop market program 1 3
3 Select channels of distribution 1 8
4 Patent 1 12
5 Pilot production 1 4
6 Test market 5 4
7 Ad promotion 2 4
8 Set up for production 4, 6 16

The project team has requested that you create a network for the project, and determine if the project can
be completed in 45 weeks.

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

KRYSTEL BERGHER PROFILE Accomplished Customer Service Expert committed to the delivery of quality service. Professional and Ethical.

KRYSTEL BERGHER PROFILE Accomplished Customer Service Expert committed to the delivery of quality service. Professional and Ethical. Seeking to assist or help a new customer service department in creating and achieving the much-needed customer service goals. CONTACT ADDRESS: 15851 Southwest 139th Place, Miami FL 33177. PHONE: 305-992-6010 EMAIL: [email protected] om

Business Law BUS 3301 VII Question 12 The principal agent relationship, the employer-employee relationship, and the employer-independent contractor

Business Law BUS 3301 VII Question 12 The principal agent relationship, the employer-employee relationship, and the employer-independent contractor relationship are three types of agency relationships commonly found in business settings. Why is it important for business professionals to know what type of agency relationship they are forming?   Your response must

pfa TASK 1: By Tuesday Evening Reflection and Discussion Forum Week 3

pfa TASK 1: By Tuesday Evening Reflection and Discussion Forum Week 3 Assigned Readings: Chapter 8. Understanding Markets and Industry Changes. Chapter 9. Market Structure and Long-Run Equilibrium. Chapter 10. Strategy: The Quest to Keep Profit from Eroding. Initial Postings: Read and reflect on the assigned readings for the week.